NNPCL has spent $1bn on AKK gas pipeline project – Kyari

Malam Mele Kyari, Group CEO, Nigerian National Petroleum Company Limited with other stakeholders at the inspection of ongoing construction of the Ajaokuta-Kaduna-Kano (AKK) Gas Pipeline and Station project site in Kogi

The Nigerian National Petroleum Company Limited (NNPC Ltd) says it has so far spent over 1.1 billion dollars on the ongoing construction of the Ajaokuta-Kaduna-Kano (AKK) Gas Pipeline and Station project from its cash-flow.

The NNPC Limited GCEO, Malam Mele Kyari said this on Monday while touring some of its project sites in Kogi, with newsmen and other stakeholders.

Kyari was accompanied by some top officials of the NNPC Limited and Oilserv Limited, (Pipelines and Facilities), the contractor of the project.

Kyari said the company would continue to fund the massive project which it was delivering in phases and has been active even though it did not have third party finance for the project.

“So far, NNPC Ltd has funded over 1.1billion dollars on the project and to date none of the project activities is abandoned as reported and we reassure all stakeholders that we have a line of sight to project delivery on schedule.

“NNPC Limited remains highly committed towards the delivery of strategic National infrastructure projects through responsive project delivery, active collaboration with government security agencies and communities as well as deployment of technology for delivering the project.

“This is is one of the most massive projects of proportion value to our country for economic growth. It is a must-deliver project and we have continued to fund in spite of not having third party finance support, we will deliver this project.

“We do not owe a dollar to our contractors, there are over 30 sites that are active today in this project, we are very hopeful and optimistic to deliver this project,” he assured.

The GCEO decried the fact that due to insecurity, it had lost some site workers thereby expressed sadness over thier demise and consoled their families whom he said the company shared in their grief.

He said 70 per cent of the welding work had been completed adding that once welding was completed, it could actually flow gas through the pipeline.

He said on completion the pipeline would deliver two billon cubic feet of gas, powering industries, powering power plants and creating gas based industries.

Related posts

Bassa Agog as Echocho Commissions Famous VIP Guest House

Edo Governor Challenges Supreme Court And President Tinubu’s Local Government Autonomy Agenda

Energy Advocates Condemn Collapse of $1.5b Port Harcourt Refinery, Demand Accountability

This website uses cookies to improve User experience. Learn More